Who? Foremost Clean Energy
Where? The Murphy Lake Project is located approximately 30 km northwest of Points North Landing
What type of activities will occur? Mineral exploration activities, including:
Diamond Drilling
• Maximum of 30 drill locations
• 20 drill collars on land
• 10 drill collars on ice
• Maximum drill pad size – 30 m x 30 m (900 m²)
• Up to 10 km of new trails and 8 km of ice roads
• Up to 50 km existing trails utilized
• Helicopter assisted, helicopter pads will be required
• Drill holes may be located within the 30-100 m of shoreline buffer zone
• Borehole Geophysical surveys
Line Cutting and Ground Geophysical Surveys
• Access to grid locations will be helicopter supported or by existing access trails. No new trails are anticipated
• Up to 60 km of new grid lines
• Up to 63 km existing grid lines
• Up to 60 km line slashing
One Temporary Work Camp
• Up to 1 ha (100 m x 100 m) in size
• Historical location, no clearing anticipated
When will these activities occur (Estimated Permit Length)? June 2025 to Dec 2027