Who? Eagle Plains
Where? The George Lake Project is located approximately 80 km southwest of Wollaston Lake
What type of activities will occur? Mineral exploration activities, including:
• The crew will access the property via highway 995 off of highway 905 or by float or ski equipped aircraft as well as helicopter out of La Ronge or Missinipe
• The drilling crew will consist of up to 16 people on site for a duration of 6 weeks
• The geophysical crew will consist of up to 5 people on site for a duration of 3 weeks
• Work is proposed to take place intermittently between July 2025 - December 2026
• Multiple temporary work camps are being requested, each occupying less than 0.5 hectares
• Up to 18 drill holes are being proposed, with 16 on land and 2 on ice
• Helicopter pads may be established to assist with the drilling program
• Approximately 7 km of new winter trail will be established
• Up to 29 km of new line will be established for the geophysical program and will include line cutting and slashing.
When will these activities occur (Estimated Permit Length)? July 2024 to December 2026